EPS Power Services did a startup on a Square D 8000 Power Meter. The technician used a Megger MPRT 8445. Injecting current through the Current Transformer (CT) shorting block at the ATS. Then injectied voltage into the 3-phase voltage wires. Finally, used a Megger MS-2 injected 50 amps through the CT to see it match on the meter screen. 

Upgrade Aging Equipment

When it’s time to upgrade or replace aging equipment, Our Modernization Solutions sustain your existing gear by upgrading components matching current technologies.

BCS Switchgear tests equipment ensuring your gear meets manufacturer, PEARL, NETA and other industry standards.We calibrate equipment for accurate reading.

Replacement Parts

We know when needing a part for an obsolete or current manufacture breaker, you need the right part and you need it now. Most parts can be shipped in the same day from our stock.

We buy and sell equipment. Our experience allows us to confidently buy large lots resulting from plant closures and auctions. New and surplus in factory condition.

 
"Thank you for getting us back online so quickly -- John P. -- Facility Manager"
5/5
"The breakers you reconditioned are working perfectly" -- Alex V. -- Plant Manager
5/5
Call Now ButtonClick to Call

Loading